Legal Insight: Protecting Homebuyers – Understanding Late Delivery and Liquidated Agreed Damages (LAD)

new home, for sale, real estate, nature, mortgage, buy, sell, house, estate, sale, new, family, property, residential, building, sign, agent, purchase, construction, selling, business, loan, homes for sale, realtor, sky, finance, buyer, architecture, residence, door, brown business, brown home, brown house, brown construction, brown news, brown finance, brown door, brown company, brown sales, brown new

Purchasing a property is often one of the most significant financial decisions an individual will make in their lifetime. For buyers of newly launched property developments, this milestone can also bring certain risks, one of the most common being delays in the delivery of vacant possession.

This article explores the legal implications of late delivery of vacant possession, including whether a developer can lawfully extend the delivery period, the statutory rights and protections afforded to purchasers under Malaysian law and the legal remedies available to enforce those rights.

In Peninsular Malaysia, housing development is primarily regulated by the Housing Development (Control & Licensing) Act 1966 (Act) and the Housing Development (Control & Licensing) Regulations 1989 (“Regulations”). These laws aim to regulate and license the business of housing development and to protect the interests of purchasers[1].

The Sale and Purchase Agreement (SPA) is the principal legal instrument defining the rights and obligations of both developers and purchasers. For licensed housing developments, the SPA must follow the statutory forms prescribed in the Regulations.

For properties sold by licensed developers, the delivery timeline is determined by the type of property title: –

  1. Property with strata title: Governed under Schedule H of the Regulations. Clause 25(1) requires the developer to deliver vacant possession within 36 months from the date of the SPA[3]

Where a developer fails to deliver vacant possession within the stipulated period, according to Clause 24 (2) of Schedule G of the Regulations and Clause 25 (2) of Schedule H of the Regulations, the Developer shall be liable to pay the Purchaser liquidated damages calculated from day to day at the rate of ten per centum (10%) per annum of the purchase price, running from the expiry of the delivery period stated in the SPA until the date the purchaser actually takes vacant possession[4].

In practice, many purchasers pay a booking fee or deposit before signing the SPA. This raises an important question: Should LAD be calculated from the date of booking fee payment or from the SPA date?

The Federal Court in PJD Regency Sdn Bhd v Tribunal Tuntutan Pembeli Rumah & Anor and Other, resolved this issue by holding that LAD calculation should begin from the date the purchaser pays the booking fee or deposit—being the point at which the purchaser has given written intention to purchase, not strictly from the SPA date[5]. This landmark decision protects homebuyers from potential delays caused by administrative gaps between booking and execution of the SPA.


Under Regulation 11(3) of the Regulations, the Controller of Housing may, in special circumstances, waive or modify the terms of the statutory contract of sale by issuing a written certificate[6].

In the case of Ang Ming Lee & Ors v Menteri Kesejahteraan Bandar, Perumahan dan Kerajaan Tempatan & Anor and other appeals, the developer applied to the Controller of Housing for an extension of time (EOT) of 12 months for delivery of vacant possession of the units to the purchasers. The developer appealed against the rejection to the Minister to the Minister of Urban Wellbeing, Housing and Local Government. By a letter signed by a person on behalf of the controller, the developer’s appeal was allowed.

The Federal Court held that the controller has no legal authority to modify any provision in Schedule H contract of sale to the developer. Regulation 11(3) of the Regulations, conferring power on the controller to waive and modify the terms and conditions of the contract of sale is ultra vires the Act. The Minister did not have the authority to delegate this power to the Controller. [7]

However, it is to be take note that the principle in Ang Ming Lee case shall only be applied prospectively and not retrospectively. This is because in the recent Federal Court case of Obata-Ambak Holdings v Prema Bonanza held that the principle in Ang Ming Lee will not be applied to extensions granted by Controller prior to the principle of the case which means the extensions granted by the Controller before Ang Ming Lee’s case is valid.[8].

Despite that the Controller has no power to grant extension of time to the developer for extension of time, the Minister retains the discretion to grant extensions. In the Court of Appeal case of Bludream City Development Sdn. Bhd. v. Kong Thye & Ors and Other, despite that the Controller has no power to grant extension of time, this does not take away the power of the Minister to give direction in extending the time for vacant possession in order to safeguard the purchasers’ interest. The Minister’s valid powers are not diminished merely because an earlier delegation to the Controller was invalid[9].

Before committing to a property purchase, purchasers are strongly advised to verify whether a developer has been blacklisted before committing to a purchase. A list of blacklisted developers is available on the official website of the Ministry of Housing and Local Government (KPKT):

👉 https://teduh.kpkt.gov.my/peringatan-pemaju

If the developer refuses to pay LAD voluntarily, the purchaser has the right to file a complaint with the Tribunal for Homebuyer Claims. However, there is a limitation on the amount that a purchaser can claim, which is RM50,000.00.[10] The claim must be made within 12 months from the earlier of:

  1. the date of issuance of the certificate of completion and compliance (CCC) of the property or facilities;
  2. The expiry of the defects liability period as set out in the SPA; or
  3. The date of termination of the SPA, if it is terminated before the CCC is issued[11].

If the claim is not filed within this 12-month period, the purchaser’s remaining option is to initiate a civil action in court, subject to a six (6) year limitation period from the date of breach[12].

Timely delivery of property is not merely a commercial expectation—it is a contractual obligation under the law. The Housing Development (Control and Licensing) Act 1966 and its Regulations prescribe strict delivery timelines and impose liability for late delivery through LAD.

Recent Federal Court decisions have reinforced these protections, making clear that any attempt to vary or extend the completion period without lawful approval from the Minister is unenforceable. Purchasers should remain vigilant, fully understand their rights under the SPA and the law, and act promptly to seek remedies where those rights are breached.